December 19, 2024

Report Wire

News at Another Perspective

Mega piped water initiatives removed from over in Sundargarh

By Express News Service

ROURKELA:  Another robust summer season could also be in retailer for residents of Sundargarh district because the 4 mega rural piped water initiatives protecting all its 17 blocks are shifting at a snail’s tempo. The 4 initiatives have been taken up at a mixed price of Rs 2,328 crore with the lion’s share coming from Odisha Mineral Bearing Areas Development Corporation (OMBDAC) fund and the remaining from District Mineral Foundation (DMF) fund. Rural Water Supply & Sanitation (RWSS) government engineer (EE), Sundargarh division Hemanta Barik stated a agency known as Megha Engineering is implementing the undertaking in Rajgangpur, Kutra and Hemgir blocks of Sundargarh sub-division at a price of round Rs 390 crore.

Around 75-80 per cent work has been accomplished in Rajgangpur and Hemgir, whereas 90 per cent is over in Kutra. Megha Engineering had began the undertaking greater than two years again and it has been given a revised completion goal of October 2023. Similarly, JMC Projects is executing the undertaking in Sundargarh, Subdega, Lefripada, Bargaon, Balishankara and Tangarpali blocks.

The work was began one 12 months in the past with a completion goal of October 2023 at a price of round Rs 779 crore. Barik stated JMC has accomplished round 30 per cent works and should search extension. He attributed the delay to native disputes and technical points together with approval of designs and drawings. In Rourkela division of RWSS, Voltas Ltd has been implementing the mega piped water undertaking in Kuanrmunda, Naugaon, Gurundia and Koida blocks in addition to a part of Lahunipada blocks of Panposh and Bonai sub-divisions at a price of over Rs 660 crore.

Voltas has already missed the completion goal of 24 months and to date has made lower than 50 per cent progress. Similarly, JMC Projets almost a 12 months in the past began the mega piped water undertaking in Bisra, Bonai and Lathikata blocks of Panposh sub-division and a part of Lahunipada block in Bonai at a price of round Rs 500 crore. With hardly 30-40 progress it’s unlikely to attain the goal of August 2023. Birmitrapur MLA Shankar Oram stated in Bisra, Naugaon and Kuanrmunda blocks of his constituency the piped water works are shifting at a snail’s tempo and haphazardly with no adherence to high quality norms. He stated complaints raised by him are being ignored.

ROURKELA:  Another robust summer season could also be in retailer for residents of Sundargarh district because the 4 mega rural piped water initiatives protecting all its 17 blocks are shifting at a snail’s tempo. The 4 initiatives have been taken up at a mixed price of Rs 2,328 crore with the lion’s share coming from Odisha Mineral Bearing Areas Development Corporation (OMBDAC) fund and the remaining from District Mineral Foundation (DMF) fund. Rural Water Supply & Sanitation (RWSS) government engineer (EE), Sundargarh division Hemanta Barik stated a agency known as Megha Engineering is implementing the undertaking in Rajgangpur, Kutra and Hemgir blocks of Sundargarh sub-division at a price of round Rs 390 crore.

Around 75-80 per cent work has been accomplished in Rajgangpur and Hemgir, whereas 90 per cent is over in Kutra. Megha Engineering had began the undertaking greater than two years again and it has been given a revised completion goal of October 2023. Similarly, JMC Projects is executing the undertaking in Sundargarh, Subdega, Lefripada, Bargaon, Balishankara and Tangarpali blocks.

The work was began one 12 months in the past with a completion goal of October 2023 at a price of round Rs 779 crore. Barik stated JMC has accomplished round 30 per cent works and should search extension. He attributed the delay to native disputes and technical points together with approval of designs and drawings. In Rourkela division of RWSS, Voltas Ltd has been implementing the mega piped water undertaking in Kuanrmunda, Naugaon, Gurundia and Koida blocks in addition to a part of Lahunipada blocks of Panposh and Bonai sub-divisions at a price of over Rs 660 crore.googletag.cmd.push(perform() googletag.show(‘div-gpt-ad-8052921-2’); );

Voltas has already missed the completion goal of 24 months and to date has made lower than 50 per cent progress. Similarly, JMC Projets almost a 12 months in the past began the mega piped water undertaking in Bisra, Bonai and Lathikata blocks of Panposh sub-division and a part of Lahunipada block in Bonai at a price of round Rs 500 crore. With hardly 30-40 progress it’s unlikely to attain the goal of August 2023. Birmitrapur MLA Shankar Oram stated in Bisra, Naugaon and Kuanrmunda blocks of his constituency the piped water works are shifting at a snail’s tempo and haphazardly with no adherence to high quality norms. He stated complaints raised by him are being ignored.