Balasore prepare tragedy: CRS report signifies faults at varied ranges

4 min read

The investigation by the Commissioner of Railway Safety (CRS) into the June 2 accident involving the horrific triple prepare accident in Odisha has reportedly discovered faults from the signalling and telecommunication division (S&T) for the grave tragedy. The Commissioner submitted its report on Thursday. The accident involving Chennai-bound Coromandel Express, the Bengaluru-Howrah Superfast, and an iron-ore good prepare claimed 292 lives and injured over 1,200 passengers in Bahanaga Bazar station close to Balasore in Odisha.

The accident occurred after the Coromandel Express entered the loop line on the station as a substitute of going straight on the principle line, hit the products prepare parked there at full pace, and its derailed coaches hit the Bengaluru-Howrah Superfast which was simply passing the station. It was evident the signalling was wrongly set for the prepare on the station.

Talking in regards to the report, a railway official said, “The report was submitted and has found lapses on the part of a few departments along with some staff in charge of the relay room. The sabotage angle, if any, will only be probed by the Central Bureau of Investigation (CBI).”

The premier investigative company can be wanting into the incident along with the CRS inquiry after the Railway Board really useful a CBI probe to look into doable sabotage angle. The authorities famous, nevertheless, that the Railways had chosen to not make the report public to be able to stop any affect or interference with the CBI investigation into the catastrophe.

“We will not be disclosing the CRS report because of another ongoing independent enquiry. This is to ensure that this report does not in any way influence or interfere with the other report. We will take cognisance of both the reports and make an overall evaluation of the incident and then take whatever steps necessary,” knowledgeable one other railway officer.

Senior authorities typically have entry to those findings to make sure that the fee’s suggestions are fastidiously adopted and carried out. Within every week of any accident, the latter usually produces an intermediate evaluation previous to the ultimate one, in accordance with officers, however this time, it has simply submitted one report.

The railway board had ordered a double-locking configuration for all of its relay rooms with prepare controlling mechanisms, relay huts (containing level-crossing signalling and telecommunications gear), and level and monitor circuit indicators days earlier than the report was offered. A double locking system that might stop entry to the rooms was supposed to make the entry to the relay room impenetrable to tampering.

It had noticed that “access to the relay room” was essential to the “signalling interference” that led the Coromandel Express to make use of the loop line at Balasore and collide with a stopped items prepare, in a letter. According to the officers, the station supervisor obtained a memo informing that the interlocking system was disconnected to do some work after which obtained one other memo indicating that the system has been reconnected after the completion of the work.

But, it has been discovered that the system was tampered with to ship false messages to the station supervisor, and really the job was not accomplished on the system. “However, in reality, the technician bypassed the system because the work was not complete and he rigged the location box to get a ‘green signal’ for the Coromandel Express,” the official stated.  

The security protocol of testing the signalling system earlier than permitting a prepare to cross was not adopted. Moreover, the signalling personnel stored working even after the reconnection message was despatched, because of this, each the station’s operations workers and the signalling upkeep group shared accountability for the disaster.

“It is the protocol that whenever maintenance of assets of any nature is carried out, the operations staff is also responsible for the safety of trains along with the engineering staff concerned, be it track-related or signalling related,” a railway officer remarked.

The Shalimar-Chennai Coromandel Express entered the station’s loop route moderately than the designated fundamental line and collided with a halted freight prepare in one of many worst railway accidents in current reminiscence. The prepare derailed and components of it hit one other prepare, the Bengaluru-Howrah Superfast, which additionally derailed, leading to excessive casualty figures.

South Eastern Railway GM transferred

Following the submission of the report by the Commissioner of Railway Safety, South Eastern Railway General Manager Archana Joshi was transferred as normal supervisor to the Rail Wheel Factory in Karnataka’s Yelahanka on Friday. The Appointments Committee of the Cabinet, on the advice of the Railway Board, appointed Anil Kumar Misra, an Indian Railway Service of Electrical Engineers officer, as the brand new GM of South Eastern Railway.

 Earlier, the Railway Board had transferred 5 senior zone officers, together with the assistant normal supervisor and the divisional railway supervisor.