Close Menu
    Facebook X (Twitter) Instagram
    Trending
    • Tripura CM Firmly Says No to Roman Script for Kokborok Language
    • All Four Thieves Nabbed in Thave Temple Jewelry Heist
    • From Popcorn to Communal Rows: Mamta on AR Rahman Drama
    • SP Exposes SIR Irregularities in 4 UP Districts
    • WPL Thriller: Giants Survive Late Scare Against Capitals
    • Bade Ghulam Ali Khan Wept: Jasraj’s Legacy of Loyalty
    • Char Dham Non-Hindu Ban Sparks Row: VHP Demands Extension to Every Hindu Shrine
    • Odisha’s Industrial Boom: Majhi Opens FRP Plant Milestone
    Facebook X (Twitter) Instagram
    Report Wire
    • World
    • India
      • Chhattisgarh
      • Jharkhand
      • Bihar
    • Entertainment
    • Sports
    • Tech
    • Business
    • Health
    Report Wire
    Home»India»Bihar»Sultanganj Ganga Bridge: 3 Collapses, New Design Hopes

    Sultanganj Ganga Bridge: 3 Collapses, New Design Hopes

    Bihar January 27, 20261 Min Read
    Facebook Twitter Pinterest LinkedIn Tumblr Email
    Sultanganj Ganga Bridge: 3 Collapses, New Design Hopes
    Share
    Facebook Twitter LinkedIn Pinterest Email

    The saga of Bihar’s Sultanganj-Aguwani Ganga Bridge reads like a chronicle of perseverance amid adversity. Spanning 3.5 kilometers, this vital connector has endured 11 years of hurdles, 12 missed deadlines, and three devastating collapses since 2022. Costing Rs 1,750 crore, it’s built by SP Singla to unite Bihar’s divided halves.

    Technical probes by IIT Roorkee revealed design vulnerabilities, prompting a shift to robust composite steel beam cable-stay construction with concrete decks. This innovation, now sanctioned, addresses past weaknesses head-on.

    While approach roads totaling 20 km stand nearly finished in Sultanganj and Aguwani-Khagaria, the Ganges-crossing kilometer persists as a bottleneck. Repeated official inspections underscore the urgency.

    Disaster timeline: First collapse on April 30, 2022, between pillars 4-6 due to gusty winds. Second on June 4, 2023, engulfing pillars 10-13 in the river. Third struck August 17, 2024, at pillar 9. Each incident amplified scrutiny on workmanship and timelines.

    Authorities project 2027 completion, eyeing seamless vehicular traffic that could revolutionize connectivity between Bhagalpur and Khagaria. As construction resumes, optimism tempers skepticism born from years of letdowns. Will advanced engineering finally deliver this long-awaited infrastructure marvel?

    2027 Bridge Completion Bihar Ganga Bridge Bihar Infrastructure Bridge Collapse Bihar Ganga River Bridge IIT Roorkee Investigation SP Singla Construction Sultanganj Aguwani Bridge
    Share. Facebook Twitter Pinterest LinkedIn Tumblr Email

    RELATED NEWS

    All Four Thieves Nabbed in Thave Temple Jewelry Heist

    January 28, 2026

    Patna Engineer Student Murdered in Chhapra Robbery Bid

    January 27, 2026

    Bihar Shocker: Girl’s Video Sparks Fatal Purnia Shootout

    January 27, 2026

    Fatal Crash in Bihar: Tractor-Trolley Accident Kills 2 Kids in Samastipur

    January 25, 2026

    Tej Pratap Mocks Rahul as Cowardly ‘Chicken Rice Chef’ in Bihar

    January 25, 2026

    5-Year-Old Raped by Neighbor in Muzaffarpur, Mob Violence Ensues

    January 25, 2026
    -Advertisement-
    © 2026 Report Wire. All Rights Reserved.
    • Terms & Conditions
    • About Us
    • Privacy Policy
    • Contact

    Type above and press Enter to search. Press Esc to cancel.