Image Source : AP People are silhouetted on automobiles headlights on a darkish road throughout widespread energy outages in Rawalpindi, Pakistan, Sunday, Jan. 10, 2021. Pakistan’s nationwide energy grid skilled a significant breakdown late night time on Saturday, leaving thousands and thousands of individuals in darkness, native media reported.
One of the worst energy outages confronted by Pakistan final week was triggered as a consequence of poor upkeep and subsequent failure of the safety system within the nationwide grid, the Dawn reported on Monday. The newspaper reported that senior officers held detailed discussions after many cities and cities throughout Pakistan plunged into darkness Saturday night time following a significant technical fault within the nation’s energy era and distribution system.
The officers admitted that the blackout had uncovered the mismanagement on the a part of the federal government in working your entire energy sector of the nation on an advert hoc foundation, it stated.
The chief government officers of all of the three key firms involved — the Central Power Generation Company-Guddu, the National Transmission and Dispatch Company (NTDC) and the National Power Control Centre (NPCC) — have been engaged on advert hoc or performing cost foundation for years.
The Central Power Generation Company (CPGC) runs the Guddu Power Station the place the preliminary technical fault was reported to have taken place, resulting in Karachi, Rawalpindi, Lahore, Islamabad, Multan and different locations going through the blackout.
The NTDC operates the nation’s nationwide grid whose safety system ought to have reacted to the Guddu station’s tripping and remoted the fault. Its system, meant to cease the transmission frequency from dropping, apparently didn’t work ensuing within the cascading closure of all the facility crops throughout the nation in a matter of seconds.
The NPCC displays the movement of electrical energy from energy crops to varied distribution firms (Discos). It has to handle provide methods for correct load and frequency balancing.
Even the Discos are working with out common chief government officers for greater than two and a half years, the newspaper stated.
The NTDC is with out a common chief government officer since July 2017 whereas NPCC has not seen a full-time CEO for greater than a decade. The NPCC chief, engaged on a short lived foundation, was employed final yr from the non-public sector.
The nation’s Prime Minister Imran Khan has reportedly expressed displeasure over non-filling of the posts in energy firms.
That a human error triggered the large outage was not directly confirmed by Engineer Hammad Amer Hashmi on Sunday when he suspended seven workers of the Guddu station working below plant manager-III and blamed them for negligence.

At a information convention, Energy Minister Omar Ayub Khan stated the breakdown occurred as a consequence of a technical fault on the Guddu station, which resulted in frequency declining from 50 to zero inside seconds.
Officials stated the preliminary fault appeared to have occurred on the Guddu station’s switchyard, however the safety system of the transmission community didn’t reply to the fault.
The transmission system ought to have rejected the load from Guddu station via an computerized safety mechanism, however apparently this didn’t occur due to poor or inadequate upkeep and non-washing of transmission strains.
The Guddu-Sibi transmission line has been a well-known bother spot due to excessive fog and different environmental points and has seen tripping prior to now as effectively.
The safety system had been separating southern and northern components of the nation’s grid prior to now.
“This is clearly a failure of the protection system,” stated a retired senior officer.
He stated the transmission strains was washed yearly, generally repeatedly, relying on the fog in winters. He additionally known as into query the previous authorities claims that the safety system had been improved, notably after the 2015 breakdown.
Had the system been improved it could have gone into an island mode. Saturday’s energy outage was the third such incident since 2015, which meant the safety system was both not upgraded or the improve was inadequate, stated the retired officer.
Meanwhile, the officers stated the transmission community had been synchronised for now, however your entire transmission and distribution community would take a while, possibly till Monday, to fully stabilise as repeated load swings have been being witnessed in lots of components of the nation. 